End of Report
Signed: John Carter MEP Project Manager
| Discipline | Planned Progress (%) | Actual Progress (%) | Status | Remarks | | :--- | :---: | :---: | :---: | :--- | | Mechanical (HVAC) | 45% | 43% | 🟡 Slight Delay | Ductwork installation ongoing; lag due to ceiling obstruction. | | Electrical | 50% | 50% | 🟢 On Schedule | Cable pulling for floors 1-3 completed. | | Plumbing & Fire Fighting | 38% | 35% | 🔴 Delayed | Delay in approved shop drawings for pump room. | | Fire Alarm | 25% | 25% | 🟢 On Schedule | Device mounting on Level 4 in progress. | mep work progress report sample
(Legend: 🟢 On Track, 🟡 At Risk, 🔴 Delayed) End of Report Signed: John Carter MEP Project
Current MEP works are 46% complete; mechanical and electrical rough-ins progressing on Floors 1–6, plumbing risers 90% complete to rooftop, and HVAC ductwork on Levels 2–4 behind schedule by 5 days due to material delay. | Discipline | Planned Progress (%) | Actual