| Code | Handeling (Operation) | Kenmerk (Characteristic) | Tijd (centimin) | |------|------------------------|--------------------------|------------------| | C10 | Plaatsen zonder passing | losse pas, voldoende speling | 3.5 | | C20 | Plaatsen met passing | lichte perspassing (0.01-0.05 mm) | 7.2 | | C30 | Plaatsen met vastklikken | audibele of voelbare klik | 5.0 |
If you are referring to a specific company (like Gustav Group) or a specific software plugin, the review stands that the table is likely a functional asset for calculating rates. If "Gustav Ende" is a typo for Gustav Mahler (classical composer often used for tempo) or a misspelling of "Gustav En" (a less common reference), please verify the source name. If this is a typo for "Gustav Jensen" or another known industry figure, the table's utility remains high provided the source data is correct.
Recommendation: Adopt the table into your standard workflow, but annotate it for new users.
De Tabel Montagetijden conform Gustav Ende is decennialang een fundamentele standaard geweest binnen de Nederlandse installatietechniek voor het berekenen van arbeidstijden in klimaat- en sanitaire projecten. Hoewel de methode sinds 2003 niet meer actief wordt onderhouden, maken veel calculatiebureaus nog steeds gebruik van deze ervaringscijfers om een realistische inschatting te maken van de benodigde "ploegminuten" voor diverse montagewerkzaamheden. Wat is de Gustav Ende Methode?
De kern van de Gustav Ende-systematiek is gebaseerd op in Duitsland verzamelde ervaringscijfers. In tegenstelling tot moderne methoden die vaak arbeidskundig zijn onderbouwd, leunt Gustav Ende op historische data van daadwerkelijk uitgevoerde werkzaamheden.
Ploegminuten: De tijden worden uitgedrukt in ploegminuten in plaats van manuren.
Ervaringsnormen: De normen zijn niet strikt wetenschappelijk onderbouwd, maar reflecteren wat in de praktijk haalbaar was bij standaardprojecten.
Correctiefactoren: Omdat de basistijden uitgaan van ideale omstandigheden, worden vaak correctiefactoren toegepast voor factoren zoals bouwhoogte, bereikbaarheid en logistiek. Voorbeelden uit de Montagelijst
In de tabellen van Gustav Ende worden specifieke tijden toegekend aan verschillende componenten. Een kenmerkend aspect is dat de tabel vaak minder differentiatie kent dan moderne alternatieven; zo wordt bij radiatoren vaak alleen naar de lengte gekeken en niet naar de hoogte. Werkzaamheid / Component Normtijd (Indicatie) Luchtverhitter tot 100kg op 3m hoogte ~375 ploegminuten Luchtverhitter tot 200kg op 3m hoogte ~580 ploegminuten Luchtverhitter tot 50kg op 7m hoogte ~420 ploegminuten Inbedrijfstelling tot 114 kW ~180 ploegminuten Inbedrijfstelling tot 297 kW ~392 ploegminuten Gustav Ende versus Techniek Nederland (Uneto-VNI)
Sinds de introductie van het handboek Calculatie voor Klimaat en Sanitair door Uneto-VNI (nu Techniek Nederland) in 2007, is er een verschuiving gaande. De belangrijkste verschillen zijn: TABEL MONTAGE TIJDEN CONFORM GUSTAV ENDE
Actualiteit: De Techniek Nederland-normen worden jaarlijks geactualiseerd, terwijl Gustav Ende sinds 2003 stilstaat.
Nauwkeurigheid: Moderne normen zijn gedetailleerder. Waar Gustav Ende bijvoorbeeld 34 tabellen voor paneelradiatoren hanteert, biedt Techniek Nederland vaak meer diepgang in componentvarianten.
Transparantie: Bij Gustav Ende is de invloed van nieuwe werkmethoden of gereedschappen vaak niet meer te reconstrueren, wat bij moderne methoden wel het geval is. Toepassing in de Moderne Praktijk
Ondanks de veroudering wordt de tabel nog vaak gebruikt door ervaren calculators die de "gevoelsmatige" juistheid van de Gustav Ende-cijfers waarderen. Veel calculatiesoftware ondersteunt beide normen, waardoor bedrijven kunnen kiezen welke systematiek het beste aansluit bij hun specifieke projecthistorie.
Wilt u een specifieke vergelijking tussen Gustav Ende en de huidige Techniek Nederland normen voor een bepaald type installatie? Normering van arbeid in de installatiebranche | TVVL
Gustav Ende Table of Installation Times (Tabel Montagetijden conform Gustav Ende) is a foundational standard in mechanical and electrical engineering, primarily used in the Netherlands and Sweden for calculating labor hours and project costs. Developed in the 1970s by Swedish engineer Gustaf Ende, this methodology provides standardized "norm times" (normtijden) for thousands of specific installation tasks. Core Principles of the Gustav Ende Norms
The Gustav Ende (GE) method is designed to provide a highly accurate, granular view of the time required for technical installations. Unlike simpler estimation methods, the GE norms are often composite: Unit-Based Timing
: Installation times are typically expressed in minutes per unit (e.g., per piece of equipment) or minutes per meter (e.g., for piping or cabling). Detail and Accuracy
: It breaks down assembly into specific components, such as steel pipes with insulation or air heaters of specific weights and mounting heights. Net vs. Gross Time | Code | Handeling (Operation) | Kenmerk (Characteristic)
: While the table provides the "net" time for a task, professional estimators apply "reduction factors" or "multipliers" to account for specific site conditions, travel time, and administrative overhead. Applications in the Industry Pre-Calculation (Estimating)
: Contractors use the table during the bidding process to determine exactly how many man-hours a project will require, which is critical for competitive yet profitable pricing. Capacity Planning
: Project managers use the GE norms to schedule labor across a construction timeline, ensuring they have the right number of technicians on-site at each phase. Performance Auditing
: By comparing actual installation times against the Gustav Ende standard, companies can measure the efficiency of their workforce. Comparison with Other Standards
In the Dutch installation sector, the Gustav Ende norms are frequently compared to the
(now Techniek Nederland) norms. A key difference noted by industry experts is that GE norms are often perceived as more rigorous or "tighter," leading many firms to apply reduction factors to make them realistic for modern workflows.
For further detailed calculations, professional tools like the Technisch Adviesburo Betuwe spreadsheet
provide specific examples of these time norms across various weight and height categories. Technisch Adviesburo Betuwe If you'd like to dive deeper, I can: specific time values for common components like piping or electrical panels. Explain how to calculate reduction factors for difficult site conditions. Compare the GE method against the Techniek Nederland Let me know how you would like to narrow down this essay. Normering van arbeid in de installatiebranche | TVVL
Wat Endes tabel uniek maakte, was zijn aandacht voor cognitieve belasting. In tegenstelling tot zijn tijdgenoten besefte Ende dat vermoeidheid niet lineair verloopt. Wat Endes tabel uniek maakte, was zijn aandacht
Zijn beroemde "Gesetz der abnehmenden Hand-Auge-Synchronisation" (Wet van de afnemende hand-oog synchronisatie) leidde tot een baanbrekende aanpassing:
De tabel was dus niet alleen een meetinstrument, maar een regulator van menselijke energie.
Step 1: Break down assembly into basic elements (e.g., get screw, get washer, position, screw 3 turns, tighten).
Step 2: For each element, find the closest match in the Gustav Ende table (by part type, size, tool, and motion).
Step 3: Sum the times to get basic time for one cycle.
Step 4: Add allowances for:
Step 5: Result = standard time for the operation.
Gustav Ende tables gave basic times for a trained worker at normal pace, without rest. In practice, engineers added a Zuschlag (surcharge) of 10–20% depending on task strain, temperature, and repetition.
Final standard time = 0.115 × 1.15 ≈ 0.132 minutes (7.9 seconds)
Thus, the production quota at 100% performance = 60 / 0.132 ≈ 455 assemblies per hour.